Bermuda is just 21 miles long and 1.75 miles wide. Yet its iconic pink sand beaches, crystal and fantasy caves, historic settlements and striking coves draw close to 650,000 visitors a year. In 2012, Dr. Tucker Murphy and his father, Lawrence, formed a local charity called Friends of Bermuda Railway Trail. Their goal was to reconnect the old Bermuda Railway [which ran from 1931 to 1948] route into a single, continuous trail for pedestrians and cyclists. The Murphy family raised capital locally from private companies and individuals to fund the project. Flatts Inlet was one of six major trail breaks the Murphys identified that required a bridge to extend visitor access to the island’s natural beauty.

While turquoise waters are a hallmark of tropical locations like Bermuda, so are hurricane-force winds and the continuous onslaught of salt water. These challenges prompted the nonprofit to look for a corrosion-resistant material that could meet local safety and performance codes and withstand harsh weather.

bermuda-bridge-build-vertical

In 2017, Friends of Bermuda Railway Trail tapped Creative Composites Group to provide a fiber reinforced polymer (FRP) pedestrian bridge from its E.T. Techtonics line. There was one major hurdle.

The project specified a clear span bridge 152 ft. long and 8 ft. wide. This type of structure is one continuous span without a bridge piling or other support structure in the water except for abutment protection.

Prior to this project, E.T. Techtonics had only produced spans up to 120 ft. long with a double truss system above and below the deck. To design and fabricate what would be the longest clear span FRP bridge in the world took a team of experienced engineers, careful planning and testing.

The University of Miami and West Virginia University performed and validated section testing on some of the unique FRP bridge components and connections. The assembled superstructure underwent a field test as part of the evaluation. Bridge components were pultruded, fabricated and readied for assembly and final testing at CCG’s Creative Pultrusions campus.

bermuda-bridge-build-liftConstruction and installation restrictions dictated two additional tests. Because the job site was in the middle of the water, top-down construction was not an option. A lift test was conducted to make sure the crane on the Bermuda job site could effectively pick up the bridge span based on the specified rigging and pick plan.

A loading test was also performed. Wooden holding tanks were filled with water and uniformly placed along the bridge deck surface to simulate the bridge filled to capacity with people. The results met design parameters for safety and performance. The bridge was disassembled, packaged, and shipped to Bermuda.

Next week we’ll delve into details about the installation of the world’s longest FRP pedestrian bridge.

Topics: bridges, composite bridge, bridge design, frp bridge, FRP, access structures

Dustin Troutman

AboutDustin Troutman

Dustin is the Chief Sales Officer for the Creative Composites Group. He earned his Civil Engineering degree in 1993 and spent the early part of his career in heavy construction. Dustin has been with Creative for 25 years and continues to be instrumental in the market investigation and development of major pultrusion products and product lines associated with civil/structural applications, holding four patents related to pultruded systems. He is a key player in the development of codes and standards in support of the FRP pultrusion industry.

Find me on:

    Recent Posts

    MOST POPULAR ARTICLES